Project Benefits
- Improve cyclist and pedestrian network connectivity in communities along the BART line
- Improve access to regional transit, schools, downtown area and other destinations
- Create a facility that is accessible and comfortable for bicyclists and pedestrians of all ages and abilities
- Improve safety for people walking, biking and rolling
- Promote broad and accessible travel options and help reduce of greenhouse gas emissions

East Bay Greenway improvements in Oakland will include:
- shared use paths,
- separated bikeways,
- protected intersections,
- enhanced crosswalks with flashing beacons and pedestrian signals,
- ADA curb ramp upgrades,
- pedestrian scale lighting
- bus loading islands,
- new traffic signals,
- new raised medians, and
- new street trees, natural drainage features, and drought-tolerant landscaping.
- Segment-by-Segment Proposed Design
- Project Concept Plans (May 2023)
- Oakland Public Works Committee Item (Concept Plan Approval – May 2023)
- Oakland BPAC Infrastructure Committee Item (Oakland North Project Design Update - Jan 2026)
- Oakland BPAC Infrastructure Committee Item (Oakland South Project Design Update - March 2026)
- BPAC Meeting – September 15, 2022, 6 p.m.
- Popup Events
- Oakland Roots Game @ Laney College Stadium, East 10th Street and 4th Avenue, Oakland – October 1, 2022, 5-8 p.m.
- Lake Merritt BART – October 25, 2022 (PM commute period)
- Coliseum BART – October 26, 2022 (PM commute period)
- Fruitvale BART/Fruitvale Farmers Market – October 27, 2022 (PM commute period)
- Día de Los Muertos Festival, International Avenue and Fruitvale Avenue, Oakland – October 30, 2022, 10 a.m.-5 p.m.
- East Oakland Neighborhood Initiative Bay Trail Bike Party – May 20, 2023
- Black Cultural Zone BBQ, East Oakland Youth Development Center – June 30, 2023, 5-8 p.m.
- Trybe San Antonio Neighborhood Town Night – July 21, 2023, 5 p.m. start
- Neighborhood Council Presentations
- Beat 32X – April 20, 2023
- Brookfield/Columbian Garden/Sobrante Park/South Stonehurst (31Y/Z) – May 10, 2023
- Greater San Antonio (18X/Y/19X) – May 10, 2023
- Coliseum/Melrose (26X/Y) – May 25, 2023 (tabling)
- Beat 33X/34X – June 21, 2023
- Fruitvale Council – July 19, 2023
- Focus Groups (co-organized with community-based organizations)
- Trybe – July 7, 2023
- Unity Council – August 24, 2023
- Black Cultural Zone – October 22, 2023
- BPAC Infrastructure Committee Meeting – November 2, 2023
- Project Overview Presentation
- East Bay Greenway Multimodal Project: Oakland flyover video
- Mailer (Fall 2022)
- Outreach Boards (Summer 2022)
- Project Flyer (Spring/Summer 2023)
- English | Spanish | Chinese | Vietnamese
- Segment Flyers (Spring/Summer 2023)
- East 10th Street (Fallon to East 8th)
- East 8th Street (East 10th to 14th Avenue)
- East 12th Street (14th Avenue to 35th Avenue)
- San Leandro Street (98th Ave to 105th Avenue)
- San Leandro Street (105th Ave to San Leandro City Limit)
- San Leandro Street – 98th to 105th Mailer (Winter 2024)
East Bay Greenway improvements in San Leandro will include:
- separated bikeways,
- protected intersections,
- new and enhanced crosswalks with flashing beacons and pedestrian signals,
- ADA curb ramp upgrades,
- new roadway lighting,
- new bus stops and stop amenities
- bus loading islands,
- sidewalk gap closures
- new street trees, natural drainage features, drought-tolerant landscaping, and
- plaza areas.
October 2026
East Bay Greenway – San Leandro Construction Beginning
Construction of the East Bay Greenway Project to improve safety and access for people walking, biking, and taking transit along San Leandro Boulevard will start in October 2026. Construction will occur on no more than two blocks in a row at any given time in order to reduce construction impacts on the community.
What Crews Will Do
- Construct protected bike lanes
- Improve bus stop amenities
- Repave the road surface
- Build new and/or reconstruct curbs, curb ramps, and sidewalks
- Add new street striping and signs
- Add landscaping and improvements such as benches, trash cans, and bike racks.
- Update traffic signals at several intersections
What the Public Can Expect
While work is underway, you may notice:
- Traffic lanes shifted or closed to make room for crews
- Some sidewalks temporarily closed or rerouted
- Temporary changes to parking and loading zones
- Temporary bus stop closures/route detours for AC Transit bus route 28
Access to buildings and pedestrian routes will be maintained throughout construction with temporary routes provided as needed.
Construction Schedule
- Construction will start in October 2026 and is expected to finish by November 2027. To minimize impacts, construction will occur on no more than two blocks in a row at any given time.
- San Leandro Boulevard will be reduced to one lane in each direction within active work zones.
- Work hours are limited to 7 a.m.–7 p.m., Monday–Friday. Work may also occur 8 a.m. –7 p.m. Saturday and Sunday (if required).
- Information about specific construction locations will be available approximately five days before work begins.
How to Prepare
The safety of the community, workers, and travelers is Alameda CTC’s top priority throughout construction, and our project team is committed to minimizing disruptions. Every effort will be made to reduce inconveniences to residents, businesses, and commuters.
Residents and businesses can plan for work in their area and minimize disruptions to their daily activities by considering the following resources:
- Watch for notices. Residents and businesses near the project will receive a notice by mail about two weeks before construction begins with project details, work schedule and contact information for who to reach with questions and feedback. Door hangers will also provide notice five days before work begins on each block.
- Plan for deliveries around construction. Plan for a different delivery date or a different loading zone. For more information or assistance with scheduling, please contact the Alameda CTC Community Outreach Team at EBGWinfo@alamedactc.org or 1-888-642-4555.
- Plan for temporary parking changes. Some street parking may be temporarily unavailable during construction. No Parking signs will be posted at least 72 hours in advance, giving residents and businesses time to identify alternate parking nearby and avoiding towing. Please leave time to park and walk to your destination.
- Expect to see construction workers and heavy equipment in the area.
Questions? We’re Here to Help
Our Community Outreach Team is here to help with questions about construction, upcoming work in your area, or how to plan for temporary changes.
- Email: EBGWinfo@alamedactc.org
- Phone: 1-888-642-4555
- San Leandro Boulevard Project Final Design Exhibit (Summer 2026)
- East 14th Street Project Design Exhibit (Summer 2026)
- San Leandro Council Item (Concept Plan Approval - June 21, 2022)
- San Leandro BPAC (San Leandro and E 14th Design Update - Nov 2025)
- Popups
- Bay Fair Farmer’s Market – February 26, 2022, 9 a.m.-1 p.m.
- San Leandro BART station – March 3, 2022, 4-7 p.m.
- John Muir Middle School, 1444 Williams Street, San Leandro – Saturday, March 12, 2022, 10 a.m.-12 p.m. (In coordination with the City of San Leandro Crosstown Corridors)
- Downtown Farmers Market, 300 Estudillo Avenue (San Leandro Main Library), San Leandro – Wednesday, April 6, 2022, 3-7 p.m.
- San Leandro High School, 2200 Bancroft Avenue, San Leandro – Saturday, April 16, 2022, 10 a.m.-12 p.m. (In coordination with the City of San Leandro Crosstown Corridors)
- San Leandro Cherry Festival – June 3, 2023
- East 14th/Hesperian Triangle Plaza Event – June 17, 2023
- Focus Groups
- Bike/Pedestrian/Transit Focus Group – Monday, April 18, 2022, 6-7 p.m.
- Business Focus Group – Thursday, April 21, 2022, 8-9 a.m.
- Boys and Girls Club – Wednesday, October 18, , 2023
- San Leandro Chamber of Commerce Project Update Presentation – Friday, November 3, 2023
- East 14th Project Update Flyer (Summer 2026)
- East 14th Project Update Mailer (Summer 2026)
What is the East Bay Greenway Project?
The East Bay Greenway (EBGW) is a regional trail which, when completed, will link seven BART stations throughout the East Bay, as well as downtown areas, schools, and other major destinations, improving safety and connectivity across multiple communities stretching from the Lake Merritt BART station to South Hayward.
Led by Alameda CTC in partnership with local jurisdictions, this transformational project will make it safer and more convenient for people walking, biking, rolling, and taking transit. It will also make it easier to reach BART, downtown areas, schools, and other nearby destinations.
How will the EBGW project benefit the community?
The project will improve safety and access to destinations for people walking, biking, and taking transit. Currently, options for safe and continuous routes for people walking and biking are limited and do not provide separation from vehicle traffic. These conditions can make walking and biking difficult, especially for students, older adults, and lower-income individuals. The region needs more safe and accessible travel options for people walking, biking, rolling, and taking transit.
The project will also improve sidewalks and curb ramps, and enhance bus stops and lighting along the corridor, providing a more comfortable environment for people walking, biking, rolling, and taking transit.
The EBGW will address these gaps in the region’s transportation network by:
- Improving cyclist and pedestrian network connectivity in communities along the BART line.
- Improving access to regional transit, schools, downtown areas, and other destinations.
- Creating a facility that is accessible and comfortable for bicyclists and pedestrians of all ages and abilities.
- Improving safety for people walking, biking and rolling.
- Promoting broad and accessible travel options and helping reduce greenhouse gas emissions.
Where is the project located in the City of San Leandro? Where will the improvements be located?
Within San Leandro, the East Bay Greenway will span approximately 3.5 miles, connecting Downtown San Leandro to the Bayfair area via San Leandro Boulevard and East 14th Street.
When will EBGW construction begin in San Leandro? How long will construction last?
San Leandro’s portion of the East Bay Greenway will be constructed in two phases.
The first phase of work along San Leandro Boulevard from the Oakland city limits to East 14th Street will start in October 2026 and is expected to conclude in November 2027.
Construction will occur on no more than two blocks in a row at any given time to minimize impacts to the community.
Construction for improvements along East 14th Street are expected to begin in spring of 2027.
What will crews do?
This project will bring new improvements to San Leandro, including:
- Installation of protected bike lanes
- Improved bus stops
- Repaved road surfaces
- New and reconstructed curbs, curb ramps, and sidewalks
- New street striping and signs
- New landscaping and streetscape features such as benches, trash cans, and bike racks
- Updated drainage
- New signal modifications and safety improvements at various intersections
How will construction impact the public?
The safety of the community, workers, and travelers is our top priority throughout construction, and our project team is committed to minimizing disruptions. Every effort will be made to reduce inconveniences to residents, businesses, and commuters.
While work is underway, you may notice:
- Traffic lanes shifted to make room for crews.
- Some sidewalks temporarily closed or rerouted.
- Temporary changes to parking and loading zones.
- Temporary bus stop closures/route detours for AC Transit Route 28.
The project will require some heavy construction including demolition, excavation, pavement markings, and striping. This can result in noise and dust. Alameda CTC will ensure contractor compliance with applicable laws and regulations.
Construction will take place between 7:00 a.m. – 7:00 p.m. Monday through Friday. Work may also occur between 8:00 a.m. – 7:00 p.m. Saturday and Sunday, if required.
Traffic control measures may be in place during construction including temporary lane and sidewalk closures. For the safety of the workers, please reduce speeds, practice caution, and follow posted detour signage.
How will the community be notified about EBGW construction?
Residents and businesses near the project area will receive a notice by mail about two weeks before construction begins with project details, work schedule and information for whom to contact with questions. Door hangers will also provide notice five days before work begins on each block.
For more information or assistance with scheduling, please contact the Alameda CTC Community Outreach Team at EBGWinfo@alamedactc.org or 1-888-642-4555.
How will traffic and parking be impacted by construction activities?
Some street parking may be temporarily unavailable during construction. No Parking signs will be posted at least 72 hours in advance, giving residents and businesses time to identify alternate parking nearby and avoiding towing.
Please leave time to park and walk to your destination.
The safety of our community, workers, and travelers is our top priority throughout construction, and our project team is committed to minimizing disruptions. Every effort will be made to reduce inconveniences to residents, businesses, and commuters.
How is this project funded?
The San Leandro segment is one part of the full East Bay Greenway Project, stretching from Lake Merritt BART to South Hayward. Alameda CTC has leveraged Measure BB sales tax funds to bring state Active Transportation Program, federal Reconnecting Communities and Neighborhoods, state Solutions for Congested Corridors Program, regional Safe Routes to Transit and Bay Trails, and federal One Bay Area Grant funds to Alameda County to fund the full project.
What if I have questions?
We appreciate your patience and understanding as we work to deliver these important improvements.
We welcome questions from the community. If you have any questions or concerns, please email: EBGWinfo@alamedactc.org or call 1-888-642-4555. A member of the project team will get back to you as soon as possible.
East Bay Greenway improvements will include a variety of elements designed to improve overall safety, create comfortable facilities for cyclists and pedestrians of all ages and abilities, and enhance the overall streetscape. Project features will include separated bikeways, enhanced crosswalks, ADA curb ramp and lighting upgrades, sidewalk repair, bus loading islands, and street beautification/greening features. Please contact us at EBGWinfo@alamedactc.org with any questions or comments.
- Concept Plan (November 2023)
- Project Flyer (November 2023)
- Related Projects
- Castro Valley Farmers Market – Saturday, August 6, 2022, 9 a.m.-1 p.m.
- REACH Ashland Youth Center, Health and Resource Fair – Wednesday, August 10, 2022, 12:30-4 p.m.
- Bayfair Farmers Market – Saturday, August 13, 2022, 9 a.m.-1 p.m.
- Unincorporated Area BPAC – Thursday, September 22, 2022, 6 p.m.
- Eden Area MAC Standing Meeting – Tuesday, February 14, 2023
- Unincorporated Area BPAC – Thursday, December 14, 2023, 6 p.m.
- Hayward Public Library – Thursday, August 11, 2022, 1-5 p.m.
- Hayward Farmers Market – Saturday, August 27, 2022, 9 a.m.-1 p.m.
- South Hayward BART Station – Tuesday, August 30, 2022, 4-7 p.m.
- CBO Popup Event – Thursday, September 15, 2022, 12 p.m.
- Additional CBO Popup Events
- Hawaiian May Day Festival – Saturday, May 11, 2024, 11:00 a.m.-3:30 p.m.
- Eden Greenway, Free Hot Meals – Monday, May 20, 2024, 11:30 a.m.-2:30 p.m.
- Flyers (Spring 2026)
- Flyers (Spring 2025)
- Cross Sections (Spring 2025)
- Flyers and Cross Sections (Spring 2025)
East Bay Greenway Urban Trail (Phase 2)
A longer-term East Bay Greenway Urban Trail (Phase 2) would construct an off-street regional trail facility in the BART corridor connecting between Fruitvale BART and South Hayward BART, a distance of approximately 13-miles. Phase 2 generally provides the same biking and walking connections as Phase 1, but offers the potential for a linear-park style facility with separate bridges at major street crossings, recreation amenities, and wider, more separated trail facility. Alameda CTC studied and environmentally cleared Phase 2 from 2016-2018. Phase 2 is being pursued on a longer timeframe due to the high-cost and need to acquire right-of-way from Union Pacific Railroad. Alameda CTC studied two design options as part of prior environmental documents. A rail-to-trail option assumes the abandonment and acquisition of the entire Union Pacific Oakland Subdivision north of Industrial Parkway in Hayward. A rail-with-trail option assumes that the Oakland Subdivision remains an active rail line and right-of-way is acquired to construct a trail in a shared rail-trail corridor. Both options would require Union Pacific to agree to provide necessary ROW and local jurisdictions to agree to own and maintain the facility.- Final CE (Approved November 2018) Final State Environmental (CEQA) Document
- Draft Final IS/MND (Adopted March 2018 by Alameda CTC)
- November 7, 2017: Open House at San Leandro Senior Community Center
- November 8, 2017: Open House at Eden United Church of Christ
- November 15, 2017: Open House at Fruitvale Senior Center
- November 16, 2017: Open House at Hayward City Hall